Timeline
Jun
2025
Construction Begins
Construction begins with installation of construction barriers/walls.
Sep
2025
Drywall, Ceilings and Soffit Complete
Oct
2025
Glass Partitions Up
Glass partition work will begin mid-September and will be complete by the end of October.
Nov
2025
Possible Library Closure for Airhandler/Smoke Curtain Work
Morris Library may be closed for one day during the week of Thanksgiving for airhandler/smoke curtain work.
Dec
2025
Construction Completion Goal
The renovation work will be substantially complete by the end of December 2025.
Feb
2026
Special Collections Renovation Opens
The newly renovated Special Collections area will open in Spring Semester 2026.